Beware Project Impacts Due to Rising Material Costs and Long Lead Times

Steeply rising material prices and unexpected shortages for certain material deliveries are wreaking havoc on the construction industry.

Matthew K. Grashoff

Written by Matthew K. Grashoff

Published: July 14, 2026

Steeply rising material prices and unexpected shortages for certain material deliveries are wreaking havoc on the construction industry. A recent article from the Associated General Contractors of America illustrates the threat these rising material prices can pose to contractors. Other projects have been impacted by unexpected shortages—and corresponding delayed deliveries—of certain items, notably steel joists. Contractors should watch changing material costs and delivery dates and communicate this information to both current and prospective clients as soon as possible. It is also important review contracts for terms related to material cost escalations and delivery delays in order to prepare for these issues.

The AGC article notes that the cost of contractor’s material purchases for nonresidential construction rose nearly 13% from April 2020 to February 2021. Bid prices remained relatively stable in that same time period, however, rising only 0.5%. The increasing material costs are particularly severe for contractors working with copper and steel. In the same time frame, the Producer Price Index (PPI) for copper and brass mill shapes rose 37% while the PPI for steel mill products rose 20%. Furthermore, the benchmark price for hot-rolled steel this quarter hit its highest price in the last 13 years. For a contractor or subcontractor that submits a fixed-price bid but doesn’t purchase materials until several months later, these cost increases may cause substantial impacts to project budgets. These increases could eliminate a contractor’s profit from a project and create severe financial hardship.

Many contractors are also facing supply issues caused by the COVID-19 pandemic, shipping delays due to recent events in the Suez Canal and ongoing delays at major California ports, and unexpected shortages caused by certain companies cornering the market for particular items. According to the Census Bureau, unfilled orders for steel in the last quarter were at the highest level in five years. At the same time, steel inventories were at a three-and-a-half-year low. Notably, a certain major online retailer recently purchased all steel joists available in the US through late 2021. These factors have led to long delivery delays that, for many if not most contractors, were unexpected and unforeseen when bids were submitted and schedules were finalized. Current conditions in the industry show that this problem is not likely to end soon.

What Can You Do?

In light of these problems, contractors should review their contracts for provisions relating to material cost escalation adjustments and delays due to unanticipated and uncontrollable material deliveries. A material escalation clause will shift the risk from the contractor or supplier of goods and services back to upstream parties and provide a clear mechanism for addressing these issues, rather than requiring the parties to go through a lengthy claim process before reaching resolution. Every material escalation clause is different and must be evaluated on its own terms, but there are often similar features in such clauses. For instance, these clauses are often “cost-based” or “index-based.” A cost-based clause compares actual incurred cost with the bid cost, and enables the contractor/supplier to receive payment for extra costs incurred. An index-based clause tracks and adjusts prices based on existing material price indexes and PPIs published by the Bureau of Labor Statistics. These terms can enable contractors to build smaller contingencies into their bids while providing the owner the ability to share in any savings should the price of materials begin to drop. Delay provisions should be evaluated to determine whether delays due to material deliveries are excusable and/or compensable.

If your contract does not contain a material escalation clause or a delay provision that encompasses material-delivery delays, also evaluate whether the contract has a force majeure clause. In some contracts, the force majeure clause is written broadly enough that it may apply to delays or added costs caused by unforeseen and uncontrollable market factors such as material-cost escalations and delivery delays. Upstream parties may push back on whether market factors truly represent force majeure events, though, and force the parties to engage in a claims process.

Regardless of whether or how your contract handles material-cost escalations and delivery delays, monitoring actual costs and schedule versus the original estimate and schedule is crucial in managing these issues. Keeping track of progress can help identify potential issues early and may avoid job loss or stoppage. Furthermore, contractors should always proactively raise these issues with upstream parties as soon as the issues arise in order to avoid any risk of waived claims. If the project is still in the bidding phase, contractors should also discuss the concern of material price escalation and delivery delays when negotiating the contract and schedule. Again, it is critical to be proactive. By getting ahead of price escalation and delivery delays before they happen, or at least promptly communicating and addressing them once they do, contractors can save a lot of headache for themselves and their projects.

Trending Articles

Recognizing Legal Leaders: The 2027 Best Lawyers Awards in Australia, Japan and Singapore


by Jamilla Tabbara

Market drivers, diversity trends and the elite practitioners shaping the legal landscape.

Illustrated maps of Australia, Japan and Singapore displayed with their national flags, representing

Musk v. Altman: The Lawyers Behind the Case


by Jamilla Tabbara

Meet the Trial Lawyers Shaping One of AI's Biggest Legal Disputes.

Portrait photos of Elon Musk and Sam Altman positioned in front of the OpenAI logo.

The Best Lawyers in France 2027: Peer-Reviewed Excellence


by Jamilla Tabbara

Seventeen editions of peer trust, a growing profession and a dynamic legal market.

3D Map of France with National Flag Graphic

Announcing the 2027 Best Lawyers Awards: Austria, Germany and Switzerland


by Jamilla Tabbara

Celebrating the legal professionals throughout Central Europe.

Graphic displaying three-dimensional map cutouts of Austria, Germany and Switzerland.

The Legal Teams Behind the Blake Lively–Justin Baldoni Settlement


by Grace Greer

A closer look at the legal teams and attorneys involved in the Blake Lively–Justin Baldoni litigation and its resolution.

Split-screen image of Blake Lively and Justin Baldoni

When Is It Too Late to Stop Foreclosure?


by Bryan Driscoll

Understanding the foreclosure timeline, critical deadlines and the legal options that may still protect your home.

Miniature house model on orange background surrounded by thumbtacks representing foreclosure

Can You Go to Jail at an Arraignment?


by Bryan Driscoll

Understanding What Happens at Your First Court Appearance.

A heavy chain lying on the ground in the foreground with a blurred figure standing in the background

How AI Is Changing the Way Clients Find Lawyers


by Jamilla Tabbara

Best Lawyers CEO Phil Greer explains how AI-driven search tools are reshaping legal marketing and why credibility markers matter.

AI chat bubble icon with stars representing artificial intelligence transforming client-lawyer conne

Colorado’s 2026 Water Rights Battles


by Bryan Driscoll

A new era of conflict begins.

Colorado Water Rights 2026: A New Era of Conflict headline

How to Choose a Personal Injury Lawyer


by Bryan Driscoll

Finding the right legal representation after an injury is a critical decision that requires careful evaluation. 

3D scene representing the deliberative process of choosing a personal injury attorney

When to Get a Lawyer for Work Injury


by Bryan Driscoll

Understanding your rights and navigating the complexity of workers’ compensation claims.

Injured worker receiving medical attention at workplace

What Happens if You Don't File Taxes


by Bryan Driscoll

The penalties are real, but so are your options. Here's what the IRS can do and what you can do about it.

A torn dollar bill revealing a watchful eye, surrounded by flying documents

What Disqualifies You From Filing Bankruptcies


by Bryan Driscoll

A guide to navigating eligibility, the means test and the legal hurdles of declaring bankruptcy.

A silhouette of a large hand pushing over a row of falling dominos toward a small figure standing be

When to Hire a Tax Attorney


by Bryan Driscoll

Understand the legal triggers, professional differences and strategic benefits of seeking legal counsel for your tax matters.

Flying tax documents symbolizing the stress and urgency of mortgage and foreclosure-related paperwor

Why Original Profiles Matter in Legal Marketing


by Jamilla Tabbara

How original, up-to-date profiles improve visibility and client trust.

Multiple web browser windows displaying lawyer profile pages

New England's Climate Litigation Surge


by Bryan Driscoll

What law firms need to know

New England's Climate Litigation Surge: What Firms Must Know headline